Archived contractor activity

Recorded PCAB ID 13487

V.R. PATRON BUILDERS & DEVELOPERS CORP. (PREVIOUSL

Project associations in the acquired DPWH snapshot, FY 2024 to FY 2025.

Project associations
105
Associations, not necessarily unique completed works
Associated project budget
₱4,956,566,900.79
Not revenue, payment, or contract value received
Joint-project associations
13

Recorded status mix

Projects by source status

Completed
37
Ongoing
63
Terminated
0

PCAB verification snapshot

current regular

Listed name
V.R. PATRON BUILDERS & DEVELOPERS CORP.
Category
AAA
Valid to
2029-11-08
Verify in the current PCAB table

Recorded project ledger

Projects associated with this recorded identity

92 sole-project associations and 13 joint-project associations. 12 project associations currently have at least one deterministic review signal.

Sole-project associated budget
₱3,914,171,786.47
Full project values for records naming only this party
Joint-project associated budget
₱1,042,395,114.32
Full project values, not an allocation to this party

Loading structured project associations...

Contractor accountability

No strongly matched accountability event is published

A missing event is not clearance. Name-only and unmatched records remain quarantined and are not shown.

Review leads

Signals associated with this contractor identity

  • We do not have enough information yetThe project has no usable coordinates

    What we noticed: CONSTRUCTION OF MISSING LINKS / NEW ROADSGENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), NASUGBU SECTION, PACKAGE 3, BATANGAS

    What this does not prove: Missing coordinates do not prove that the project is missing.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY CARSUCHE, TAAL, BATANGAS (PHASE 4)

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT POBLACION BARANGAY I, SAN JOSE, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, COMPLETION OF MULTI-PURPOSE BUILDING AND SITE FACILITIES AT BARANGAY DAGATAN, SAN JOSE, BATANGAS

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, COMPLETION OF MULTI-PURPOSE BUILDING AND SITE FACILITIES AT BARANGAY DAGATAN, SAN JOSE, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROAD, MAKALINTAL AVENUE (PROVINCIAL ROAD), SAN JOSE,

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, IMPROVEMENT OF MULTI-PURPOSE BUILDING AND SITE FACILITIES, SAN JOSE, BATANGAS

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, IMPROVEMENT OF MULTI-PURPOSE BUILDING AND SITE FACILITIES, SAN JOSE, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - NASUGBU-LIAN-CALATAGAN RD - K0106 + 200 - K0107 + 621

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROAD, BRGY. TUGTUG-BRGY. NATUNUAN (PROVINCIAL ROAD),

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF SLOPE PROTECTION WITH FLOOD CONTROL STRUCTURE ALONG PINAGTUNG-ULAN BRIDGE, M

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING (NASUGBU SPORTS COMPLEX), NASUGBU, BATANGAS (PHASE 3)

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING (NASUGBU SPORTS CENTER), NASUGBU, BATANGAS (PHASE 2)

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING (NASUGBU SPORTS COMPLEX), NASUGBU, BATANGAS (PHASE 1)

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged

Concentration context

Groups where this was the leading recorded party

Batangas 3rd DEO15.2% of contractor-party associations · FY 2025
Batangas 1st DEO12.5% of contractor-party associations · FY 2024
Batangas 3rd DEO12.7% of contractor-party associations · FY all years