Archived contractor activity

Recorded PCAB ID 13810

L.R. TIQUI BUILDERS, INC.

Project associations in the acquired DPWH snapshot, FY 2024 to FY 2025.

Project associations
105
Associations, not necessarily unique completed works
Associated project budget
₱10,076,354,250.15
Not revenue, payment, or contract value received
Joint-project associations
24

Recorded status mix

Projects by source status

Completed
48
Ongoing
53
Terminated
0

PCAB verification snapshot

current regular

Listed name
L.R. TIQUI BUILDERS, INC.
Category
AAAA
Valid to
2027-03-01
Verify in the current PCAB table

Recorded project ledger

Projects associated with this recorded identity

81 sole-project associations and 24 joint-project associations. 28 project associations currently have at least one deterministic review signal.

Sole-project associated budget
₱7,315,400,291.37
Full project values for records naming only this party
Joint-project associated budget
₱2,760,953,958.78
Full project values, not an allocation to this party

Loading structured project associations...

Contractor accountability

No strongly matched accountability event is published

A missing event is not clearance. Name-only and unmatched records remain quarantined and are not shown.

Review leads

Signals associated with this contractor identity

  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MAHARLIKA HIGHWAY, PROVINCE OF BULACAN

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • We do not have enough information yetThe project has no usable coordinates

    What we noticed: CONSTRUCTION OF FLYOVERS/ INTERCHANGES/ UNDERPASSES/ LONG SPAN BRIDGES AGUINALDO HIGHWAY, GOVERNOR'S DRIVE INTERCHANGE

    What this does not prove: Missing coordinates do not prove that the project is missing.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INERANGAN RIVER (SEGMENT 25), RAMOS, TARLAC

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION/REHABILITATION OF BARANGAY TUMANA WATER SYSTEM, BARANGAY TUMANA, MARIKINA CITY

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLEGU JURISDICTIONS) PULILAN-BALIUAG BYPASS ROAD - BARANGAY BALATONG B AND BARANGAY CALANTIPAY, CHAINAGE 6006-CHAINAGE 6700, BALIUAG, BULACAN

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • We do not have enough information yetThe project has no usable coordinates

    What we noticed: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES - BONGA MENOR FLYOVER AT PLARIDEL BYPASS, BUSTOS, BULACAN

    What this does not prove: Missing coordinates do not prove that the project is missing.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION (COMPLETION) OF MULTI-LEVEL MULTI-PURPOSE BUILDING, BARANGAY NAPINDAN, TAGUIG CITY

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: INSTALLATION OF SAN MIGUEL AVENUE, SANTAN STREET, VICTORY HILLS ROAD SAFETY DEVICES INCLUDING LATERALS, BARANGAY FORTUNE, MARIKINA CITY

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: INSTALLATION OF ROAD SAFETY DEVICES, SECOND DISTRICT, MARIKINA CITY

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: INSTALLATION OF MIRA VERDE AND TIERRA VISTA ROAD SAFETY DEVICES INCLUDING LATERALS, BARANGAY NANGKA, MARIKINA CITY

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: CONSTRUCTION OF FLOOD CONTROL ALONG TARLAC RIVER CONTROL LEFT DIKE, SAN ISIDRO SECTION (SEGMENT A), TARLAC CITY, TARLAC

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS, DAANG MAHARLIKA (LZ), PROVINCE OF BULACAN

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE ALONG SAT. MARIA SAN JOSE ROAD (SAN JOSE - CATMON SECTION), STA MARIA, BULACAN

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) PULILAN-BALIUAG BYPASS RD - CHAINAGE 7330 - CHAINAGE 9560, PULILAN-BALIUAG, BULACAN

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER (TAWIRAN WAWANG PULO SECTION) STA. 02+200 STA. 02+300, OBANDO, BULACAN

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PHASE II) AT BARANGAY PIEL, BALIUAG, BULACAN

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE - PRIMARY ROADS MANILA NORTH ROAD K0018+541 K0018+1059, K0019+000 K0019+329

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: PREVENTIVE MAINTENANCE - SECONDARY ROADS - CONGRESSIONAL AVE (S05266LZ) - K0013+(-065) - K0011+1234, QUEZON CITY

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • We do not have enough information yetThe project has no usable coordinates

    What we noticed: AWP 3/PREVENTIVE MAINTENANCE-PULILAN-BALIUAG BY-PASS ROAD, BALIUAG, BULACAN, PROVINCE OF BULACAN

    What this does not prove: Missing coordinates do not prove that the project is missing.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: REHABILITATION OF PINTONG BATO - TIGBE ROAD, SANTA MARIA, BULACAN

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONSTRUCTION OF SANTO CRISTO DIVERSION ROAD (PHASE III), BARANGAY SANTO CRISTO, CITY OF SAN JOSE DEL MONTE, BULACAN

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE - PRIMARY ROADS MANILA NORTH ROAD K0021+587 K0021+877, K0022+000 K0022+060, K0022+125 K0022+492, K0023+801 K0023+931

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE AT BARANGAY PAGALA (PUROK 3 TO PUROK 4), BALIUAG, BULACAN

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES, PLARIDEL-PULILAN BRIDGE (OLD) (BO2092LZ) ALONG DAANG MAHARLIKA, PROVINCE OF BULACAN

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • We do not have enough information yetThe project has no usable coordinates

    What we noticed: BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES, PLARIDEL-PULILAN BRIDGE (OLD) (BO2092LZ) ALONG DAANG MAHARLIKA, PROVINCE OF BULACAN

    What this does not prove: Missing coordinates do not prove that the project is missing.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONSTRUCTION OF ROAD, BARANGAY SANTO CRISTO, SAN JOSE DEL MONTE, BULACAN

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: INSTALLATION OF ROAD SAFETY DEVICES AT BARANGAY FORTUNE, MARIKINA CITY

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONSTRUCTION OF BRIDGE ALONG BALAGTAS-PLARIDEL BYPASS, BONGA MENOR, BUSTOS, BULACAN

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF SAN VICENTE CATMON BRIDGE, SANTA MARIA, BULACAN

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged

Concentration context

Groups where this was the leading recorded party

Bulacan 2nd DEO9.5% of contractor-party associations · FY 2024