Archived contractor activity

Recorded PCAB ID 22465

LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION)

Project associations in the acquired DPWH snapshot, FY 2024 to FY 2025.

Project associations
154
Associations, not necessarily unique completed works
Associated project budget
₱16,427,481,887.70
Not revenue, payment, or contract value received
Joint-project associations
22

Recorded status mix

Projects by source status

Completed
48
Ongoing
105
Terminated
0

PCAB verification snapshot

current regular

Listed name
LEGACY CONSTRUCTION CORPORATION
Category
AAA
Valid to
2027-01-31
Verify in the current PCAB table

Recorded project ledger

Projects associated with this recorded identity

132 sole-project associations and 22 joint-project associations. 22 project associations currently have at least one deterministic review signal.

Sole-project associated budget
₱13,811,821,566.34
Full project values for records naming only this party
Joint-project associated budget
₱2,615,660,321.36
Full project values, not an allocation to this party

Loading structured project associations...

Contractor accountability

No strongly matched accountability event is published

A missing event is not clearance. Name-only and unmatched records remain quarantined and are not shown.

Review leads

Signals associated with this contractor identity

  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MANJUYOD RIVER (UPSTREAM),

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMPREVENTIVE MAINTENANCE - TERTIARY ROADNOVELETA DIV RD (S01772LZ) - K0025 + (-021) - K0026 + 300

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF BINALBAGAN RIVER BANK SLOPE PROTECTION ALONG BACOLOD SOUTH ROAD, KAUSWAGAN VILLAGE, BARANGAY PROGRESO, BINALBAGAN, NEGROS OCCIDENTAL

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG PUERTO PRINCESA SOUTH ROAD - K0058+(-464) - K0058+949, ABORLAN, PALAWAN

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: INSTALLATION / APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG LACSON STREET (S00114NR) - K0001 + (-151) TO K0001 + 915

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG STO NIÑO-BANAGO RD (NORTH) - K0003 + (-706) - K0003 + 383

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY STA. EULALIA, BAAO, CAMARINES SUR

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGUSAN RIVER, PRK. 6 SECTION, BARANGAY POBLACION, MONKAYO, DAVAO DE ORO PHASE II

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ASSET PRESERVATION REHABILITATION/ RECONSTRUCTION OF ROADS W/ SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS- DAVAO-SARANGANI COASTAL ROAD(MALALAG-MALITA-JAS-G), K1697 + 420 K1697 + 681, DON MARCELINO, DAVAO OCCIDENTAL

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF CONCRETE REVETMENT, FATIMA FLOOD CONTROL, MALITA, DAVAO OCCIDENTAL

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CSSP - BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY SAN FRANCISCO, BAAO, CAMARINES SUR

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CSSP - BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY STA. EULALIA - BARANGAY SAN FRANCISCO, BAAO, CAMARINES SUR

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BAGO RIVER, CAVAN-CULO SECTION (PHASE 3)

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BAGO RIVER, CAVAN-CULO SECTION (PHASE 2)

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: CONSTRUCTION OF BANK PROTECTION STRUCTURE ALONG TINONGAN RIVER, ISABELA, NEGROS OCCIDENTAL

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROAD AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS/ FACILITIES - REHABILITATION OF TALISAY-BIGA ROAD, CALATAGAN, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION (COMPLETION) OF DPWH DAVAO DE ORO 2ND DEO BUILDING, COMPOSTELA, DAVAO DE ORO

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG BACOLOD SOUTH RD - K0062 + 522 - K0062 + 546, K0062 + 614 - K0063 + 580, K0063 + 747 - K0064 + 538,K0068 + 760 - K0069 + 121, K0071 + 632 - K0071 + 847, K0072 + 283 - K0072 + 692

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: CONSTRUCTION OF ROAD ALONG CROSSING MAGALLON - BRGY. BI-AK NA BATO RD., MOISES PADILLA, NEGROS OCCIDENTAL

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUPILAC RIVER (PHASE VI), R.T. LIM ZAMBOANGA SIBUGAY

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: INSTALLATION OF ROAD SAFETY DEVICES ALONG JCT. BAGONAWA - LA CASTELLANA - ISABELA RD - K0064 + 000 - K0064 + 718 AND JCT PONTEVEDRA - LA CASTELLANA RD - K0062 + 038 - K0062 + 443, LA CASTELLANA, NEGROS OCCIDENTAL

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING - PAYATAS RD - K0026 + 500 - K0027 + 559, QUEZON CITY

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged

Concentration context

Groups where this was the leading recorded party

Region IV-B11.0% of contractor-party associations · FY 2025
Negros Occidental 2nd DEO12.6% of contractor-party associations · FY 2024
Negros Island Region3.1% of contractor-party associations · FY 2024
Region IV-B7.5% of contractor-party associations · FY all years