Archived contractor activity

Recorded PCAB ID 22679

JMLD CONSTRUCTION

Project associations in the acquired DPWH snapshot, FY 2024 to FY 2025.

Project associations
18
Associations, not necessarily unique completed works
Associated project budget
₱1,117,442,291.54
Not revenue, payment, or contract value received
Joint-project associations
0

Recorded status mix

Projects by source status

Completed
2
Ongoing
14
Terminated
0

PCAB verification snapshot

current regular

Listed name
JMLD CONSTRUCTION
Category
A / B / C
Valid to
2027-02-27
Verify in the current PCAB table

Recorded project ledger

Projects associated with this recorded identity

18 sole-project associations and 0 joint-project associations. 6 project associations currently have at least one deterministic review signal.

Sole-project associated budget
₱1,117,442,291.54
Full project values for records naming only this party
Joint-project associated budget
₱0.00
Full project values, not an allocation to this party

Loading structured project associations...

Contractor accountability

No strongly matched accountability event is published

A missing event is not clearance. Name-only and unmatched records remain quarantined and are not shown.

Review leads

Signals associated with this contractor identity

  • The recorded place may not matchThe coordinates and place name may not agree

    What we noticed: CONVERG. AND SPL. SUPPORT PROG.-SUST. INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-FLOOD MITIGATION STRUCT. PROTECTING MAJ./STRAT. PUBLIC BLDGS./FACS.-CONST. OF RIVERBANK PROTECTION STRUCT. ALONG MALANGAAN RIVER(UPSTREAM), BRGY. CAMACHILE, DONA REMEDIOS

    What this does not prove: Office and project labels can differ from map boundaries. This does not prove a false location.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERG. AND SPL. SUPPORT PROG.-SUST. INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-FLOOD MITIGATION STRUCT. PROTECTING MAJ./STRAT. PUBLIC BLDGS./FACS.-CONST. OF RIVERBANK PROTECTION STRUCT. ALONG MALANGAAN RIVER(UPSTREAM), BRGY. CAMACHILE, DONA REMEDIOS

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION/REHABILITATION OF RAINWATER COLLECTORS SYSTEM (RWCS) IN PUBLIC FACILITIES 1) MALBONG ELEMENTARY SCHOOL, BRGY. MALBONG, GAINZA, CAMARINES SUR 2) CAGBUNGA ELEMENTARY SCHOOL, BRGY. CAGBUNGA, GAINZA, CAMARINES SUR 3) DAHILIG ELEMENTARY SCHOOL, BR

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE RAIN WATER COLLECTOR SYSTEM (RWCS)

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-FLOOD MITIGATION STRUCT. PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF FLOOD CONTROL STRUCT. ALONG ANYATAM-MAPANIQUE CREEK, PHASE 5, SAN ILDEFON

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE & SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJ. ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCT. PROTECTING MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF FLOOD CTRL. STRUCTURE ALONG ANYATAM-MAPANIQUE CREEK,PHASE 8,SAN ILDEFONSO,BUL.

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: BASIC INFRASTRUCTURE PROGRAM-BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF MARONQUILLO-PASONG BANGKAL ROAD, SAN RAFAEL, BULACAN

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged

Concentration context

Groups where this was the leading recorded party

No published concentration group lists this contractor as the leading recorded party.