Project associations
103
Associations, not necessarily unique completed works
Associated project budget
₱814,293,422.18
Not revenue, payment, or contract value received
Joint-project associations
1

Recorded status mix

Projects by source status

Completed
56
Ongoing
47
Terminated
0

PCAB verification snapshot

current regular

Listed name
GREENFIELD CONSTRUCTION CORPORATION(FORMERLY: GREENFIELD CONSTRUCTION)
Category
B
Valid to
2027-10-21
Verify in the current PCAB table

Recorded project ledger

Projects associated with this recorded identity

102 sole-project associations and 1 joint-project association. 10 project associations currently have at least one deterministic review signal.

Sole-project associated budget
₱785,343,422.18
Full project values for records naming only this party
Joint-project associated budget
₱28,950,000.00
Full project values, not an allocation to this party

Loading structured project associations...

Contractor accountability

No strongly matched accountability event is published

A missing event is not clearance. Name-only and unmatched records remain quarantined and are not shown.

Review leads

Signals associated with this contractor identity

  • We do not have enough information yetThe project has no usable coordinates

    What we noticed: BASIC EDUCATIONAL FACILITIES FUND (BEFF) - CONSTRUCTION OF SCHOOL BUILDING, ALANGILAN SENIOR HIGH SCHOOL, BRGY. ALANGILAN, BATANGAS CITY, PROVINCE OF BATANGAS

    What this does not prove: Missing coordinates do not prove that the project is missing.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, BATANGAS - LOBO RD - K0128+500 - K0129+000, K0129+821 - K0130+055

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • We do not have enough information yetThe project has no usable coordinates

    What we noticed: BASIC EDUCATIONAL FACILITIES FUND (BEFF) - CONSTRUCTION OF SCHOOL BUILDING, SAN LUIS CENTRAL SCHOOL, BATANGAS

    What this does not prove: Missing coordinates do not prove that the project is missing.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY SAMBAT, SAN PASCUAL, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SYSTEM IN BARANGAY HUKAY, CALATAGAN, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BAWI, PADRE GARCIA, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM - CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONCRETING OF BRGY. PANGHAYAN FMR, BRGY. PANGHAYAAN, TAYSAN, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION (COMPLETION) OF WATER SYSTEM INCLUDING GENERATOR SET, BRGY. LOCLOC, SAN LUIS, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SYSTEM IN BARANGAY BIGAIN I, SAN JOSE, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged

Concentration context

Groups where this was the leading recorded party

Batangas 2nd DEO22.3% of contractor-party associations · FY 2024
Batangas 2nd DEO20.8% of contractor-party associations · FY all years