Archived contractor activity

Recorded PCAB ID 31527

MICLOVER GENERAL CONSTRUCTION & IRON WORKS

Project associations in the acquired DPWH snapshot, FY 2024 to FY 2025.

Project associations
59
Associations, not necessarily unique completed works
Associated project budget
₱1,298,150,201.04
Not revenue, payment, or contract value received
Joint-project associations
3

Recorded status mix

Projects by source status

Completed
20
Ongoing
36
Terminated
0

PCAB verification snapshot

current regular

Listed name
MICLOVER GENERAL CONSTRUCTION & IRON WORKS
Category
AAA / B
Valid to
2027-09-04
Verify in the current PCAB table

Recorded project ledger

Projects associated with this recorded identity

56 sole-project associations and 3 joint-project associations. 13 project associations currently have at least one deterministic review signal.

Sole-project associated budget
₱1,182,341,504.90
Full project values for records naming only this party
Joint-project associated budget
₱115,808,696.14
Full project values, not an allocation to this party

Loading structured project associations...

Contractor accountability

No strongly matched accountability event is published

A missing event is not clearance. Name-only and unmatched records remain quarantined and are not shown.

Review leads

Signals associated with this contractor identity

  • We do not have enough information yetThe project has no usable coordinates

    What we noticed: CONSTRUCTION OF ACCESS ROAD FROM MARIKINA - INFANTA ROAD TO SITIO CABADING, BARANGAY INARAWAN ANTIPOLO CITY (SECOND DISTRICT)

    What this does not prove: Missing coordinates do not prove that the project is missing.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE & SPECIAL SUPPORT PROG-BASIC INFRAS PROG (BIP)-MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING WEST WING) AT BARANGAY CARASUCHE,TAAL,BATANGAS (PHASE 2)

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (YOUTH CENTER) AT CARASUCHE, TAAL, BATANGAS

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • We do not have enough information yetThe project has no usable coordinates

    What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MOLINO 3, BACOOR CITY, CAVITE

    What this does not prove: Missing coordinates do not prove that the project is missing.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF 4-STOREY 16-CLASSROOM SCHOOL BUILDING IN AGUINALDO ELEMENTARY SCHOOL, BARANGAY TABON 2, KAWIT, CAVITE

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LUCSUHIN, CALATAGAN, BATANGAS

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIESCONSTRUCTION (COMPLETION) OF CAVITE CITY HOSPITAL, CAVITE CITY, CAVITE

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN PEDRO, LAGUNA

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING IN SAN JUAN SENIOR HIGH SCHOOL, BARANGAY LIPAHAN, SAN JUAN, BATANGAS

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: REHABILITATION OF DRAINAGE CANAL SYSTEM, BARANGAY SAN LORENZO, SAN PEDRO, LAGUNA

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN ANTONIO, SAN PEDRO, LAGUNA

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESREHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALAGASANG, IMUS, CAVITE

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESREHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALAGASANG, IMUS, CAVITE

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • We do not have enough information yetThe record says completed, but this source has no satellite image

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALAGASANG, IMUS, CAVITE

    What this does not prove: A missing image does not prove that work was not completed.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALAGASANG, IMUS, CAVITE

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged

Concentration context

Groups where this was the leading recorded party

Laguna 2nd DEO14.0% of contractor-party associations · FY 2024