Recorded PCAB ID 42334
JEUSMACK BUILDERS & CONSTRUCTION SUPPLY
Project associations in the acquired DPWH snapshot, FY 2024 to FY 2025.
- Project associations
- 58 Associations, not necessarily unique completed works
- Associated project budget
- ₱1,387,656,522.44 Not revenue, payment, or contract value received
- Joint-project associations
- 8
Recorded status mix
Projects by source status
- Completed
- 24
- Ongoing
- 34
- Terminated
- 0
PCAB verification snapshot
current regular
- Listed name
- JEUSMACK BUILDERS & CONSTRUCTION SUPPLY
- Category
- B
- Valid to
- 2027-07-05
Recorded project ledger
Projects associated with this recorded identity
50 sole-project associations and 8 joint-project associations. 9 project associations currently have at least one deterministic review signal.
- Sole-project associated budget
- ₱745,692,265.32 Full project values for records naming only this party
- Joint-project associated budget
- ₱641,964,257.12 Full project values, not an allocation to this party
Loading structured project associations...
Contractor accountability
No strongly matched accountability event is published
A missing event is not clearance. Name-only and unmatched records remain quarantined and are not shown.
Review leads
Signals associated with this contractor identity
- The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INGALERA RIVER, BARANGAY ANO, SAN CARLOS CITY, PANGASINAN
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LIBAS CREEK, BARANGAY LIBAS, SAN CARLOS CITY, PANGASINAN
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY APAYA, MALASIQUI, PANGASINAN
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: CONSTRUCTION OF DRAINAGE CANAL, BRGY. MATAGDEM, SAN CARLOS CITY, PANGASINAN
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: CONCRETING OF ROAD, BRGY. STA. MARIA, MAPANDAN, PANGASINAN
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: CONSTRUCTION OF DRAINAGE STRUCTURE, PUROK 3, BARANGAY BOLOSAN, SAN CARLOS CITY, PANGASINAN
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-CAMILING-WAWA-BAYAMBANG-MALASIQUI-STA. BARBARA RD-K0201+581-K0201+679
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: 1. CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGNO RIVER, WARDING SECTION, BAYAMBANG, PANGASINAN 2. CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BARANGAY SAN GABRIEL 2ND, BAYAMBANG, PANGASINAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: CONCRETING OF BRGY. PAYAPA FMR, BRGY. PAYAPA, SAN CARLOS CITY, PANGASINAN
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged
Concentration context