Recorded PCAB ID 50737
SAMJS CONSTRUCTION SERVICES
Project associations in the acquired DPWH snapshot, FY 2024 to FY 2025.
- Project associations
- 83 Associations, not necessarily unique completed works
- Associated project budget
- ₱1,057,531,505.64 Not revenue, payment, or contract value received
- Joint-project associations
- 0
Recorded status mix
Projects by source status
- Completed
- 27
- Ongoing
- 37
- Terminated
- 0
PCAB verification snapshot
current regular
- Listed name
- SAMJS CONSTRUCTION SERVICES
- Category
- B
- Valid to
- 2027-08-06
Recorded project ledger
Projects associated with this recorded identity
83 sole-project associations and 0 joint-project associations. 27 project associations currently have at least one deterministic review signal.
- Sole-project associated budget
- ₱1,057,531,505.64 Full project values for records naming only this party
- Joint-project associated budget
- ₱0.00 Full project values, not an allocation to this party
Loading structured project associations...
Contractor accountability
No strongly matched accountability event is published
A missing event is not clearance. Name-only and unmatched records remain quarantined and are not shown.
Review leads
Signals associated with this contractor identity
- The recorded place may not matchSeveral projects use the same coordinates
What we noticed: IMPROVEMENT OF ROAD AT BARANGAY CALANTIPAY, BALIUAG, BULACAN
What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.
See why this was flagged - The recorded place may not matchSeveral projects use the same coordinates
What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING, MERCADO, HAGONOY, BULACAN
What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: REHABILITATION OF ROAD, SITIO PULO, BARANGAY BARIHAN, MALOLOS CITY, BULACAN
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - The recorded place may not matchSeveral projects use the same coordinates
What we noticed: REHABILITATION OF ROAD, BARANGAY IBA, HAGONOY, BULACAN
What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS EASTERN BULACAN ROAD - K0066+(-068) - K0066+085
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF REVETMENT AT BARANGAY TAMPOK, HAGONOY, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF MULTI-PURPOSE FACILITY, BARANGAY CAINGIN, BOCAUE, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN BATIA ELEMENTARY SCHOOL, BARANGAY BATIA, BOCAUE, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PULONG GUBAT, GUIGUINTO, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: REHABILITATION AND IMPROVEMENT OF POLO-OBANDO-BULACAN INTERJURISDICTIONAL ROADS, BULAKAN, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF AMRIS MALAMIG NIA ROAD LAT. D, BUSTOS, BULACAN (KATUBIGAN - KALSADA TUNGO SA PATUBIGAN)
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN LALAKHAN ELEMENTARY SCHOOL, BRGY. LALAKHAN, SANTA MARIA, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - The record disagrees with itselfThe project says ongoing, but progress says 100%
What we noticed: ASSET PRESERVATION PROGRAM - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - PULILAN-CALUMPIT RD - K0051+370 - K0051+875, CALUMPIT, BULACAN
What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: REHABILITATION OF OLD MUNICIPAL BUILDING AT BARANGAY IGULOT, BOCAUE, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN JOSE, HAGONOY, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN BINAGBAG NATIONAL HIGH SCHOOL, BRGY. BINAGBAG, ANGAT, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: REHABILITATION OF ROAD AT BARANGAY BAMBANG, BULAKAN, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN PEDRO, HAGONOY, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: IMPROVEMENT OF ROAD AT BARANGAY STO. ROSARIO, MALOLOS CITY, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF ROAD, BARANGAY BUNLO, BOCAUE, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - The recorded place may not matchSeveral projects use the same coordinates
What we noticed: CONSTRUCTION OF ROAD, BARANGAY BUNLO, BOCAUE, BULACAN
What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY ATLAG, MALOLOS CITY, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF DRAINAGE STRUCTURE AT BARANGAY STA. PEREGRINA, PULILAN, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: REHABILITATION OF ROAD AT BARANGAY TINEJERO, PULILAN, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS BALIWAG FLYOVER (S01491LZ) CHAINAGE 000 - CHAINAGE 341, BALIWAG, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF ROAD, BARANGAY TIGBE, NORZAGARAY, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTO. NIÑO I, CITY OF SAN JOSE DEL MONTE, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTISRY ROADS - BALAGTAS SERVICE RD - CHAINAGE 0 - CHAINAGE 370, BALAGTAS, BULACAN
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged - The recorded place may not matchSeveral projects use the same coordinates
What we noticed: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTISRY ROADS - BALAGTAS SERVICE RD - CHAINAGE 0 - CHAINAGE 370, BALAGTAS, BULACAN
What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.
See why this was flagged
Concentration context
Groups where this was the leading recorded party
No published concentration group lists this contractor as the leading recorded party.