Official DPWH delivery record

FY 2024 · Contract 24CC0056

CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY PRITIL (PHASE II), GUIGUINTO, BULACAN

Bulacan 1st DEO, Region III

Recorded project budget
₱98,999,571.90
Snapshot value, not proof of payment
Status / progress
Completed / 100.0%
Reported by the source record
Things to check
0
Questions to verify, not findings

Project details

Fields in the archived DPWH record

Original publisher
Department of Public Works and Highways
Accessed through
BetterGov DPWH dataset and API
Processed and published by
Busisi, built and maintained by Auva Labs
Category
Flood Control and Drainage
Source status
Completed
Reported progress
100.0%
Start date
2024-02-07
Completion date
2024-09-23
Coordinates
14.8541222, 120.8730472
Satellite image field
Present in source record
Recorded contractor
TOPNOTCH CATALYST BUILDERS INC. (34061)
Source of funds
Regular Infra - GAA 2024 SSP
Normalized family
family:8941a131fe5d35eb5cf32c87c9d4573f57f328585e881d8be5ca1a9448bdf383
Artifact SHA-256
5b411cf3f112fabd…

Office-linked congressional context

Bulacan 1st DEO

  • Bulacan, 1st DistrictDomingo, Danilo "Danny" A.
  • Bulacan, 2nd DistrictPancho, Augustina Dominique "Ditse Tina" C.
  • Bulacan, 5th DistrictCruz, Agatha "Agay"

District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.

Project image evidence

Image coverage review not yet recorded

No reconciled project-image review is available for this contract.

A missing image review is not evidence that no project photos exist.

Traceability

Evidence by public-money stage

  1. 01AppropriationRelated GAA source row available
  2. 02ProcurementNo exact artifact located
  3. 03AwardNot established by acquired evidence
  4. 04ImplementationDPWH delivery record available
  5. 05Inspection and acceptanceNot available in acquired procurement evidence
  6. 06Release, obligation and paymentNot available in the acquired records
  7. 07COA project observationNo reviewed project-level match located

Procurement timeline

Coverage review not yet recorded

This dossier has not passed the separate procurement evidence review.

Open the procurement evidence desk

Document acquisition

Contract evidence checklist

No lifecycle document checklist is available for this dossier.

Contract outcome pack

No cross-source outcome review available

Comparable procurement and delivery evidence has not been acquired for this dossier.

Contractor identities

Parties stated in the project record

PCAB 34061

TOPNOTCH CATALYST BUILDERS INC.

147 archived project associations · ₱11,846,761,183.47

Open contractor activity

Things that need checking

Questions raised by this record

No published item needs checking under the current rules.

COA audit evidence

Coverage review not yet recorded

This dossier has not yet passed the separate COA catalogue review.

Open the COA audit evidence desk

Related delivery history

Other records sharing the family identity

  • FY 2024 · 24CC0053CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY PRITIL, GUIGUINTO, BULACANBulacan 1st DEO, Region III
    ₱96,499,556.14Open record

Contract acquisition evidence

Exact structured identifier

Accepted secondary rows
1
Quarantined secondary rows
0
Last reconciled
2026-11-03
structured exact

24CC0056 - Construction of Riverbank Protection Structure at Barangay Pritil, (Phase II), Guiguinto, Bulacan

TOPNOTCH CATALYST BUILDERS INC. · DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO

Contract amount
₱95,049,793.52
Award date
2024-01-30
Status
active
Source row SHA-256
34bada809f6f2fdd…
Archived mirror SHA-256
9bfa9e7cbf5041dc…
Archived mirror revision
b98de579579e8c7e…
DPWH universe SHA-256
5b411cf3f112fabd…

Provenance

Identifiers and archived source fingerprints

Original publisher
Department of Public Works and Highways
Accessed through
BetterGov public datasets and APIs
Contract ID
24CC0056
Artifact SHA-256
5b411cf3f112fabd…