Official DPWH delivery record

FY 2024 · Contract 24FK0023

LOCAL PROGRAM-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-COMPLETION OF SORSOGON CONVENTION CENTER SORSOGON CITY

Sorsogon DEO, Region V

Recorded project budget
₱19,234,603.55
Value in this dated record, not proof of payment
Status / progress
Completed / 100.0%
Reported by the source record
Things to check
1
Questions to verify, not findings

Project details

What the official project record says

Published by
Department of Public Works and Highways
Data accessed through
BetterGov DPWH dataset and API
Category
Buildings and Facilities
Source status
Completed
Reported progress
100.0%
Start date
2024-02-28
Completion date
2024-04-26
Coordinates
12.9810417, 124.0233694
Satellite image field
Present in source record
Recorded contractor
CHEEREL CONSTRUCTION & SUPPLY (40242)
Source of funds
Regular Infra - GAA 2024 LP
Related project group
family:93ba8c23f9ae73e8794716399b5bb0f023bd6fd5322619d9c57e90635a35e696
Saved-file check code
5b411cf3f112fabd…

Office-linked congressional context

Sorsogon DEO

  • Sorsogon, 1st DistrictEscudero, Bernadette G.

District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.

Project image evidence

Image review not yet recorded

No checked project-image review is available for this contract.

A missing image review is not evidence that no project photos exist.

Traceability

Evidence by public-money stage

  1. 01AppropriationNo exact appropriation link established
  2. 02ProcurementNo exact document located
  3. 03AwardNot established by the available evidence
  4. 04ImplementationDPWH delivery record available
  5. 05Inspection and acceptanceNot available in the procurement evidence Busisi has
  6. 06Release, obligation and paymentNot available in the records Busisi has
  7. 07COA project observationNo reviewed project-level match located

Procurement timeline

Review not yet recorded

This project page has not passed the separate procurement evidence review.

Open the procurement evidence page

Document checks

Contract document checklist

No contract document checklist is available for this project.

Contract outcome review

No comparison between procurement and delivery records is available

Busisi does not yet have comparable procurement and delivery evidence for this project page.

Contractor identities

Parties stated in the project record

Things that need checking

Questions raised by this record

  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: Coordinate 12.9810417, 124.0233694 is shared by: 24FK0021, 24FK0023.

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged

COA audit evidence

Review not yet recorded

This project page has not yet passed the separate COA report review.

Open the COA audit evidence page

Related delivery history

Other records sharing the family identity

No related delivery records were found in the same project group.

Contract match check

Exact structured identifier

Accepted secondary rows
1
Conflicting secondary rows held back
0
Last checked
2026-11-03
structured exact

24FK0023-Local Program-National Building Program-Buildings and Other Structures-Multi-Purpose/Facilities-Completion of Sorsogon Convention Center Sorsogon City

CHEEREL CONSTRUCTION & SUPPLY · DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SORSOGON 1ST DEO

Contract amount
₱19,234,603.55
Award date
2024-02-14
Status
active
Source row SHA-256
3352d6c5aa87967d…
Saved mirror file check code
9bfa9e7cbf5041dc…
Saved mirror version check code
b98de579579e8c7e…
DPWH universe SHA-256
5b411cf3f112fabd…

Sources and checks

Where this information came from

Official information published by
Department of Public Works and Highways
Data accessed through
BetterGov public datasets and APIs
Contract number
24FK0023
Saved-file check code
5b411cf3f112fabd…