Official DPWH delivery record

FY 2024 · Contract 24MH0112

CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM

Sultan Kudarat 2nd DEO, Region XII

Recorded project budget
₱2,893,016.36
Snapshot value, not proof of payment
Status / progress
Completed / 100.0%
Reported by the source record
Things to check
0
Questions to verify, not findings

Project details

Fields in the archived DPWH record

Original publisher
Department of Public Works and Highways
Accessed through
BetterGov DPWH dataset and API
Processed and published by
Busisi, built and maintained by Auva Labs
Category
Water Provision and Storage
Source status
Completed
Reported progress
100.0%
Start date
2024-06-05
Completion date
2024-12-10
Coordinates
6.4017678, 124.2519572
Satellite image field
Present in source record
Recorded contractor
ALBANOR CONSTRUCTION (41645)
Source of funds
Regular Infra - GAA 2024 SSP
Normalized family
family:c5de56dc1f4230e4ce9b103cf730e76b5a32fc6fc3ebbd6a85eb91a9d0a8d793
Artifact SHA-256
5b411cf3f112fabd…

Office-linked congressional context

Sultan Kudarat 2nd DEO

  • Sultan Kudarat, 2nd DistrictSuansing, Bella Vanessa B.

District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.

Project image evidence

Image coverage review not yet recorded

No reconciled project-image review is available for this contract.

A missing image review is not evidence that no project photos exist.

Traceability

Evidence by public-money stage

  1. 01AppropriationNo exact appropriation link established
  2. 02ProcurementNo exact artifact located
  3. 03AwardNot established by acquired evidence
  4. 04ImplementationDPWH delivery record available
  5. 05Inspection and acceptanceNot available in acquired procurement evidence
  6. 06Release, obligation and paymentNot available in the acquired records
  7. 07COA project observationNo reviewed project-level match located

Procurement timeline

Coverage review not yet recorded

This dossier has not passed the separate procurement evidence review.

Open the procurement evidence desk

Document acquisition

Contract evidence checklist

No lifecycle document checklist is available for this dossier.

Contract outcome pack

No cross-source outcome review available

Comparable procurement and delivery evidence has not been acquired for this dossier.

Contractor identities

Parties stated in the project record

Things that need checking

Questions raised by this record

No published item needs checking under the current rules.

COA audit evidence

Coverage review not yet recorded

This dossier has not yet passed the separate COA catalogue review.

Open the COA audit evidence desk

Related delivery history

Other records sharing the family identity

  • FY 2025 · 25DE0167CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM - CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMBatangas 2nd DEO, Region IV-A
    ₱2,605,500.00Open record
  • FY 2025 · 25MH0124CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMSultan Kudarat 2nd DEO, Region XII
    ₱2,604,508.21Open record
  • FY 2025 · 25GI0081CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMIloilo 4th DEO, Region VI
    ₱2,597,606.33Open record
  • FY 2025 · 25NE0071CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMDinagat Islands DEO, Region XIII
    ₱2,592,472.54Open record
  • FY 2025 · 25JK0033CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM - CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMZamboanga City 1st DEO, Region IX
    ₱2,526,445.79Open record
  • FY 2024 · 24A00599CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMRegion I, Region I
    ₱6,368,638.30Open record
  • FY 2024 · 24JF0063CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMZamboanga Sibugay 2nd DEO, Region IX
    ₱2,873,495.12Open record
  • FY 2024 · 24NE0078CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMDinagat Islands DEO, Region XIII
    ₱2,860,083.45Open record
  • FY 2024 · 24CN0212CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMAurora DEO, Region III
    ₱2,855,514.50Open record

Contract acquisition evidence

Exact structured identifier

Accepted secondary rows
1
Quarantined secondary rows
0
Last reconciled
2026-11-03
structured exact

24MH0112 - Construction of Rainwater Collector System, Datu Gas Tubo Elementary School, Senator Ninoy Aquino, Sultan Kudarat, Datu Sipot Elementary School, Palimbang, Sultan Kudarat, Datu Etang Integr

ALBANOR CONSTRUCTION · DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SULTAN KUDARAT 2ND

Contract amount
₱2,893,016.36
Award date
2024-05-29
Status
active
Source row SHA-256
b0b275c94a0bdbb8…
Archived mirror SHA-256
9bfa9e7cbf5041dc…
Archived mirror revision
b98de579579e8c7e…
DPWH universe SHA-256
5b411cf3f112fabd…

Provenance

Identifiers and archived source fingerprints

Original publisher
Department of Public Works and Highways
Accessed through
BetterGov public datasets and APIs
Contract ID
24MH0112
Artifact SHA-256
5b411cf3f112fabd…