FY 2025 · Contract 25CP0081
CONVERG. AND SPECIAL SUPPORT PROG.-SUST. INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./FACILITIES-REHAB. OF SIBUL-DRT ROAD, DONA REMEDIOS TRINIDAD, BULACAN (PHASE 10)
Bulacan 3rd DEO, Region III
- Recorded project budget
- ₱95,061,787.38 Snapshot value, not proof of payment
- Status / progress
- On-Going / 12.2% Reported by the source record
- Things to check
- 1 Questions to verify, not findings
Project details
Fields in the archived DPWH record
- Original publisher
- Department of Public Works and Highways
- Accessed through
- BetterGov DPWH dataset and API
- Processed and published by
- Busisi, built and maintained by Auva Labs
- Category
- GAA 2025 SSP
- Source status
- On-Going
- Reported progress
- 12.2%
- Start date
- 2025-04-14
- Completion date
- Not stated
- Coordinates
- Not available in the source record
- Satellite image field
- Not present in source record
- Recorded contractor
- ONE FRAME CONSTRUCTION INC. (57070) / CORE CHECK CONSTRUCTION INC. (59155)
- Source of funds
- Regular Infra - GAA 2025 SSP
- Normalized family
- family:405633bf337ec5b76770bfba4839e199c952126feb1b6e5941f1d248727d86bd
- Artifact SHA-256
5b411cf3f112fabd…
Office-linked congressional context
Bulacan 3rd DEO
- Bulacan, 3rd DistrictViolago, Mark Cholo I.
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Project image evidence
Image coverage review not yet recorded
No reconciled project-image review is available for this contract.
A missing image review is not evidence that no project photos exist.
Traceability
Evidence by public-money stage
- 01AppropriationNo exact appropriation link established
- 02ProcurementNo exact artifact located
- 03AwardNot established by acquired evidence
- 04ImplementationDPWH delivery record available
- 05Inspection and acceptanceNot available in acquired procurement evidence
- 06Release, obligation and paymentNot available in the acquired records
- 07COA project observationNo reviewed project-level match located
Procurement timeline
Coverage review not yet recorded
This dossier has not passed the separate procurement evidence review.
Open the procurement evidence deskDocument acquisition
Contract evidence checklist
No lifecycle document checklist is available for this dossier.
Contract outcome pack
No cross-source outcome review available
Comparable procurement and delivery evidence has not been acquired for this dossier.
Contractor identities
Parties stated in the project record
ONE FRAME CONSTRUCTION INC.
91 archived project associations · ₱8,003,603,028.74
Open contractor activityCORE CHECK CONSTRUCTION INC.
36 archived project associations · ₱3,259,844,922.76
Open contractor activityThings that need checking
Questions raised by this record
- We do not have enough information yetThe project has no usable coordinates
What we noticed: The archived DPWH record has no usable latitude and longitude pair.
What this does not prove: Missing coordinates do not prove that the project is missing.
See why this was flagged
COA audit evidence
Coverage review not yet recorded
This dossier has not yet passed the separate COA catalogue review.
Open the COA audit evidence deskRelated delivery history
Other records sharing the family identity
No related delivery records were found under the same normalized family identity.
Contract acquisition evidence
Multiple exact source rows
- Accepted secondary rows
- 3
- Quarantined secondary rows
- 0
- Last reconciled
- 2026-11-03
ITB and Bid Docs for Contract ID 25CP0081 - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/or Bridges from the Natio
ONE FRAME CONSTRUCTION INC. · DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ( BULACAN 3RD DEO) -
- Contract amount
- ₱95,061,787.38
- Award date
- 2025-03-27
- Status
- active
- Source row SHA-256
7247ae8afb022456…
ITB and Bid Docs for Contract ID 25CP0081 - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/or Bridges from the Natio
ONE FRAME CONSTRUCTION INC. · DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ( BULACAN 3RD DEO) -
- Contract amount
- ₱95,061,787.38
- Award date
- 2025-03-27
- Status
- active
- Source row SHA-256
c086222eebb58482…
ITB and Bid Docs for Contract ID 25CP0081 - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/or Bridges from the Natio
ONE FRAME CONSTRUCTION INC. · DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ( BULACAN 3RD DEO) -
- Contract amount
- ₱95,061,787.38
- Award date
- 2025-03-27
- Status
- active
- Source row SHA-256
c69b0bcf2eedd442…
- Archived mirror SHA-256
9bfa9e7cbf5041dc…- Archived mirror revision
b98de579579e8c7e…- DPWH universe SHA-256
5b411cf3f112fabd…
Provenance
Identifiers and archived source fingerprints
- Original publisher
- Department of Public Works and Highways
- Accessed through
- BetterGov public datasets and APIs
- Contract ID
- 25CP0081
- Artifact SHA-256
5b411cf3f112fabd…