Something to check, not a finding

We do not have enough information yet · Contract 24CC0369

The record says completed, but this source has no satellite image

CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, BARANGAY SAN PEDRO (PUROK 2), BUSTOS, BULACAN

Recorded project budget
₱77,198,882.23
Status / progress
Completed / 100.0%
Location
Bulacan 1st DEO, Region III

Why Busisi flagged this

What we noticed

The record is completed but the snapshot reports no satellite image.

Why check it: A listed image field is missing from the acquired record for a completed project.

What to check next: Check project images, inspection records, and completion documents.

Technical details

Absence from this field is not proof that implementation evidence does not exist.

Rule code
completed_without_satellite_image
Snapshot fingerprint
5b411cf3f112fabd…
Open the project record

Office-linked congressional context

Bulacan 1st DEO

  • Bulacan, 1st DistrictDomingo, Danilo "Danny" A.
  • Bulacan, 2nd DistrictPancho, Augustina Dominique "Ditse Tina" C.
  • Bulacan, 5th DistrictCruz, Agatha "Agay"

District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.

Recorded contractor identities

Every party stated in the project record

Other things to check

0 other flags on this contract

No published item needs checking under the current rules.