We do not have enough information yet · Contract 24CC0600
The record says completed, but this source has no satellite image
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER (TRIBUTARY), PACKAGE G, PUROK 4, BARANGAY SAN JOSE, PLARIDEL, BULACAN
- Recorded project budget
- ₱96,499,335.50
- Status / progress
- Completed / 100.0%
- Location
- Bulacan 1st DEO, Region III
Why Busisi flagged this
What we noticed
The record is completed but the snapshot reports no satellite image.
Why check it: A listed image field is missing from the acquired record for a completed project.
What to check next: Check project images, inspection records, and completion documents.
Technical details
Absence from this field is not proof that implementation evidence does not exist.
- Rule code
- completed_without_satellite_image
- Snapshot fingerprint
5b411cf3f112fabd…
Office-linked congressional context
Bulacan 1st DEO
- Bulacan, 1st DistrictDomingo, Danilo "Danny" A.
- Bulacan, 2nd DistrictPancho, Augustina Dominique "Ditse Tina" C.
- Bulacan, 5th DistrictCruz, Agatha "Agay"
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Recorded contractor identities
Every party stated in the project record
TOPNOTCH CATALYST BUILDERS INC.
147 archived project associations · ₱11,846,761,183.47
Open contractor activityOther things to check
0 other flags on this contract
No published item needs checking under the current rules.