The record disagrees with itself · Contract 24DD0070
The project says ongoing, but progress says 100%
CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY LAPOLAPO 1, SAN JOSE, BATANGAS
- Recorded project budget
- ₱4,802,395.45
- Status / progress
- On-Going / 100.0%
- Location
- Batangas 4th DEO, Region IV-A
Why Busisi flagged this
What we noticed
Status is On-Going; reported progress is 100.0%.
Why check it: The status and progress fields should describe the same point in the work.
What to check next: Check the latest project update, completion record, and inspection documents.
Technical details
The status field may update later than the progress field.
- Rule code
- status_progress_conflict
- Snapshot fingerprint
5b411cf3f112fabd…
Office-linked congressional context
Batangas 4th DEO
- Batangas, 4th DistrictBolilia, Amado Carlos IV A.
- Batangas, 6th DistrictRecto, Ryan S.
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Recorded contractor identities
Every party stated in the project record
MAC BUILDERS CIVIL ENGINEERING CONSTRUCTION
44 archived project associations · ₱330,479,996.49
Open contractor activityOther things to check
0 other flags on this contract
No published item needs checking under the current rules.