We do not have enough information yet · Contract 24DG0038
The record says completed, but this source has no satellite image
CONST OF DRAINAGE STRUCTURE ALONG ROAD-TAG-BATS VIA TUY RD K0064+010-K0064+480
- Recorded project budget
- ₱18,423,659.08
- Status / progress
- Completed / 100.0%
- Location
- Cavite 2nd DEO, Region IV-A
Why Busisi flagged this
What we noticed
The record is completed but the snapshot reports no satellite image.
Why check it: A listed image field is missing from the acquired record for a completed project.
What to check next: Check project images, inspection records, and completion documents.
Technical details
Absence from this field is not proof that implementation evidence does not exist.
- Rule code
- completed_without_satellite_image
- Snapshot fingerprint
5b411cf3f112fabd…
Office-linked congressional context
Cavite 2nd DEO
- Cavite, 8th DistrictTolentino, Aniela Bianca D.
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Recorded contractor identities
Every party stated in the project record
JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS
85 archived project associations · ₱2,645,877,288.71
Open contractor activityOther things to check
0 other flags on this contract
No published item needs checking under the current rules.