The record disagrees with itself · Contract 24DM0090
The project says ongoing, but progress says 100%
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT POBLACION WIDE, CATANAUAN, QUEZON
- Recorded project budget
- ₱72,375,000.00
- Status / progress
- On-Going / 100.0%
- Location
- Quezon 3rd DEO, Region IV-A
Why Busisi flagged this
What we noticed
Status is On-Going; reported progress is 100.0%.
Why check it: The status and progress fields should describe the same point in the work.
What to check next: Check the latest project update, completion record, and inspection documents.
Technical details
The status field may update later than the progress field.
- Rule code
- status_progress_conflict
- Source-file check code
5b411cf3f112fabd…
Office-linked congressional context
Quezon 3rd DEO
- Quezon, 3rd DistrictArrogancia, Reynante U.
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Recorded contractor identities
Every party stated in the project record
ST. GERRARD CONSTRUCTION GEN. CONTRACTOR & DEVELOPMENT CORP. (FORMERLY:ST. GERRARD CONSTRUCTION) ([REVOKED] 31762)
69 saved project associations · ₱7,371,763,909.88
Open contractor activityOther things to check
0 other flags on this contract
No published item needs checking under the current rules.