The record disagrees with itself · Contract 24DO0050
The project says ongoing, but progress says 100%
CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES - REHABILITATION OF ROAD, BARANGAY SAN ISIDRO, RODRIGUEZ, RIZA
- Recorded project budget
- ₱28,509,769.18
- Status / progress
- On-Going / 100.0%
- Location
- Rizal 2nd DEO, Region IV-A
Why Busisi flagged this
What we noticed
Status is On-Going; reported progress is 100.0%.
Why check it: The status and progress fields should describe the same point in the work.
What to check next: Check the latest project update, completion record, and inspection documents.
Technical details
The status field may update later than the progress field.
- Rule code
- status_progress_conflict
- Snapshot fingerprint
5b411cf3f112fabd…
Office-linked congressional context
Rizal 2nd DEO
- Rizal, 2nd DistrictTanjuatco, Emigdio III P.
- Rizal, 3rd DistrictGarcia, Jose Arturo Jr. S.
- Rizal, 4th DistrictHernandez, Dennis "Tom" L.
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Recorded contractor identities
Every party stated in the project record
DAHL CONSTRUCTION CORP. (FORMERLY: DAHL CONSTRUCTION)
31 archived project associations · ₱1,430,920,276.97
Open contractor activityOther things to check
0 other flags on this contract
No published item needs checking under the current rules.