Something to check, not a finding

The record disagrees with itself · Contract 24G00085

The project says ongoing, but progress says 100%

COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS- MAASIN SUPER HEALTH CENTER, ILOILO

Recorded project budget
₱5,970,000.00
Status / progress
On-Going / 100.0%
Location
Region VI, Region VI

Why Busisi flagged this

What we noticed

Status is On-Going; reported progress is 100.0%.

Why check it: The status and progress fields should describe the same point in the work.

What to check next: Check the latest project update, completion record, and inspection documents.

Technical details

The status field may update later than the progress field.

Rule code
status_progress_conflict
Snapshot fingerprint
5b411cf3f112fabd…
Open the project record

Congressional context

No exact office attribution available

The listed office did not match a published office-to-district mapping.

Recorded contractor identities

Every party stated in the project record

PCAB 28289

S.T. SALCEDO CONSTRUCTION CORP.(FORMERLY: SHAK CONSTRUCTION & SUPPLY)

58 archived project associations · ₱1,240,787,183.08

Open contractor activity

Other things to check

0 other flags on this contract

No published item needs checking under the current rules.