Something to check, not a finding

The record disagrees with itself · Contract 24GE0026

The project says ongoing, but progress says 100%

CONSTRUCTION OF OTHER BUILDING - CONSTRUCTION OF DPWH GUIMARAS DISTRICT ENGINEERING OFFICE EXTENSION BUILDING, SAN MIGUEL, JORDAN, GUIMARAS

Recorded project budget
₱39,121,629.70
Status / progress
On-Going / 100.0%
Location
Guimaras DEO, Region VI

Why Busisi flagged this

What we noticed

Status is On-Going; reported progress is 100.0%.

Why check it: The status and progress fields should describe the same point in the work.

What to check next: Check the latest project update, completion record, and inspection documents.

Technical details

The status field may update later than the progress field.

Rule code
status_progress_conflict
Source-file check code
5b411cf3f112fabd…
Open the project record

Office-linked congressional context

Guimaras DEO

  • Guimaras, Lone DistrictNava, JC Rahman A., MD.

District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.

Recorded contractor identities

Every party stated in the project record

PCAB 7063

J.E. TICO CONSTRUCTION CO., INC. (FORMERLY: JET CO

65 saved project associations · ₱2,827,341,947.62

Open contractor activity

Other things to check

0 other flags on this contract

No published item needs checking under the current rules.