The record disagrees with itself · Contract 24HI0129
The project says ongoing, but progress says 100%
CONSTRUCTION OF 1-STOREY 3-CLASSROOM SCHOOL BUILDING IN CABADIANGAN INTEGRATED SCHOOL, BARANGAY CABADIANGAN, MUNICIPALITY OF COMPOSTELA, CEBU PROVINCE
- Recorded project budget
- ₱9,940,000.00
- Status / progress
- On-Going / 100.0%
- Location
- Cebu 5th DEO, Region VII
Why Busisi flagged this
What we noticed
Status is On-Going; reported progress is 100.0%.
Why check it: The status and progress fields should describe the same point in the work.
What to check next: Check the latest project update, completion record, and inspection documents.
Technical details
The status field may update later than the progress field.
- Rule code
- status_progress_conflict
- Snapshot fingerprint
5b411cf3f112fabd…
Office-linked congressional context
Cebu 5th DEO
- Cebu, 5th DistrictFrasco, Vincent Franco "Duke" D.
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Recorded contractor identities
Every party stated in the project record
WQC DESIGN AND CONSTRUCTION
25 archived project associations · ₱220,596,903.12
Open contractor activityOther things to check
0 other flags on this contract
No published item needs checking under the current rules.