We do not have enough information yet · Contract 24HL0019
The record says completed, but this source has no satellite image
ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: WIDENING OF PERMANENT BRIDGES: JUAN COLON BR. (B00014NR) ALONG DUMAGUETE SOUTH RD, ZAMBOANGUITA, NEGROS ORIENTAL
- Recorded project budget
- ₱35,280,000.00
- Status / progress
- Completed / 100.0%
- Location
- Negros Oriental 3rd DEO, Negros Island Region
Why Busisi flagged this
What we noticed
The record is completed but the snapshot reports no satellite image.
Why check it: A listed image field is missing from the acquired record for a completed project.
What to check next: Check project images, inspection records, and completion documents.
Technical details
Absence from this field is not proof that implementation evidence does not exist.
- Rule code
- completed_without_satellite_image
- Snapshot fingerprint
5b411cf3f112fabd…
Office-linked congressional context
Negros Oriental 3rd DEO
- Negros Oriental, 3rd DistrictDegamo, Janice
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Recorded contractor identities
Every party stated in the project record
MIGHTY HOK SUMMIT CONSTRUCTION & DEVELOPMENT CORP.
50 archived project associations · ₱1,994,782,022.71
Open contractor activityOther things to check
0 other flags on this contract
No published item needs checking under the current rules.