Something to check, not a finding

The record disagrees with itself · Contract 24K00187

The project says ongoing, but progress says 100%

PREVENTIVE MAINTENANCE- PRIMARY ROADS, BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1281 + (-141) - K1282 + 000, K1329 + (-1119) - K1329 + 000, K1342 + 832 - K1344 + 154, K1345 + 594 - K1346 + 800

Recorded project budget
₱167,190,117.07
Status / progress
On-Going / 100.0%
Location
Region X, Region X

Why Busisi flagged this

What we noticed

Status is On-Going; reported progress is 100.0%.

Why check it: The status and progress fields should describe the same point in the work.

What to check next: Check the latest project update, completion record, and inspection documents.

Technical details

The status field may update later than the progress field.

Rule code
status_progress_conflict
Snapshot fingerprint
5b411cf3f112fabd…
Open the project record

Congressional context

No exact office attribution available

The listed office did not match a published office-to-district mapping.

Recorded contractor identities

Every party stated in the project record

Other things to check

0 other flags on this contract