Something to check, not a finding

The recorded place may not match · Contract 24OD0209

Several projects use the same coordinates

CONSTRUCTION OF RETAINING WALL AT DISIPLINA VILLGAE (PHASE 2), BARANGAY UGONG, VALENZUELA CITY

Recorded project budget
₱24,007,029.25
Status / progress
On-Going / 100.0%
Location
Metro Manila 3rd DEO, National Capital Region

Why Busisi flagged this

What we noticed

Coordinate 14.6733024, 120.9869509 is shared by: 24OD0177, 24OD0209.

Why check it: The exact same point appears on more than one project record.

What to check next: Compare the project titles, places, scopes, images, and site plans.

Technical details

Shared coordinates can represent adjacent works or a common site and are not proof of duplicate funding.

Rule code
reused_coordinate
Snapshot fingerprint
5b411cf3f112fabd…
Open the project record

Office-linked congressional context

Metro Manila 3rd DEO

  • Caloocan City, 1st DistrictMalapitan, Oscar G.
  • Caloocan City, 2nd DistrictErice, Edgar R.
  • Caloocan City, 3rd DistrictAsistio, Dean
  • Valenzuela City, 1st DistrictGatchalian, Kenneth T.
  • Valenzuela City, 2nd DistrictGalang, Gerald Cloyd Alexis V.

District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.

Recorded contractor identities

Every party stated in the project record

PCAB 16759

DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERLY: DIADEMA ENTERPRISES)

71 archived project associations · ₱2,880,675,895.06

Open contractor activity

Other things to check

1 other flag on this contract

  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: Status is On-Going; reported progress is 100.0%.

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged