Something to check, not a finding

The recorded place may not match · Contract 25AI0030

Several projects use the same coordinates

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANILA RIVER, BALUNGAO-UMINGAN, PANGASINAN (PACKAGE 1)

Recorded project budget
₱95,341,669.08
Status / progress
On-Going / 100.0%
Location
Pangasinan 3rd DEO, Region I

Why Busisi flagged this

What we noticed

Coordinate 15.9280719, 120.6400758 is shared by: 25AI0030, 25AI0209.

Why check it: The exact same point appears on more than one project record.

What to check next: Compare the project titles, places, scopes, images, and site plans.

Technical details

Shared coordinates can represent adjacent works or a common site and are not proof of duplicate funding.

Rule code
reused_coordinate
Snapshot fingerprint
5b411cf3f112fabd…
Open the project record

Office-linked congressional context

Pangasinan 3rd DEO

  • Pangasinan, 5th DistrictGuico, Ramon Jr. N.
  • Pangasinan, 6th DistrictPrimicias-Agabas, Marlyn L.

District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.

Recorded contractor identities

Every party stated in the project record

Other things to check

1 other flag on this contract

  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: Status is On-Going; reported progress is 100.0%.

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged