We do not have enough information yet · Contract 25CP0151
The project has no usable coordinates
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRA. PROGRAM (BIP)-BIP FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF SLOPE REVETMENT STRUCTURE WITH IMPROVEMENT OF WATERWAYS ALONG BALAONG RIVER CONTROL,BALAO
- Recorded project budget
- ₱78,014,722.54
- Status / progress
- Not Yet Started / 0.0%
- Location
- Bulacan 3rd DEO, Region III
Why Busisi flagged this
What we noticed
The archived DPWH record has no usable latitude and longitude pair.
Why check it: Without coordinates, the recorded place cannot be checked on a map.
What to check next: Check the project page, plans, images, and agency location records.
Technical details
Missing coordinates do not indicate that a project is missing on the ground.
- Rule code
- missing_coordinate
- Snapshot fingerprint
5b411cf3f112fabd…
Office-linked congressional context
Bulacan 3rd DEO
- Bulacan, 3rd DistrictViolago, Mark Cholo I.
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Recorded contractor identities
Every party stated in the project record
TOPNOTCH CATALYST BUILDERS INC.
147 archived project associations · ₱11,846,761,183.47
Open contractor activitySKYLINE EDGE CONSTRUCTION CORP.
6 archived project associations · ₱558,137,681.02
Open contractor activityOther things to check
0 other flags on this contract
No published item needs checking under the current rules.