Something to check, not a finding

The record disagrees with itself · Contract 25FC0010

The project says ongoing, but progress says 100%

NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - TERTIARY ROADS STA. ELENA - CAPALONGA BY PASS COASTAL RD - K0281+893 - K0282+220, CAPALONGA, CAMARINES NORTE

Recorded project budget
₱19,011,455.84
Status / progress
On-Going / 100.0%
Location
Camarines Norte DEO, Region V

Why Busisi flagged this

What we noticed

Status is On-Going; reported progress is 100.0%.

Why check it: The status and progress fields should describe the same point in the work.

What to check next: Check the latest project update, completion record, and inspection documents.

Technical details

The status field may update later than the progress field.

Rule code
status_progress_conflict
Snapshot fingerprint
5b411cf3f112fabd…
Open the project record

Office-linked congressional context

Camarines Norte DEO

  • Camarines Norte, 1st DistrictTallado, Josefina B.

District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.

Recorded contractor identities

Every party stated in the project record

Other things to check

0 other flags on this contract

No published item needs checking under the current rules.