We do not have enough information yet · Contract 25HA0114
The record says completed, but this source has no satellite image
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM
- Recorded project budget
- ₱2,600,500.00
- Status / progress
- Completed / 100.0%
- Location
- Bohol 1st DEO, Region VII
Why Busisi flagged this
What we noticed
The record is completed but the snapshot reports no satellite image.
Why check it: A listed image field is missing from the acquired record for a completed project.
What to check next: Check project images, inspection records, and completion documents.
Technical details
Absence from this field is not proof that implementation evidence does not exist.
- Rule code
- completed_without_satellite_image
- Snapshot fingerprint
5b411cf3f112fabd…
Office-linked congressional context
Bohol 1st DEO
- Bohol, 1st DistrictYap, John Geesnell "Baba"
District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.
Recorded contractor identities
Every party stated in the project record
EC SOLICON BUILDERS & SUPPLY, INC.
33 archived project associations · ₱1,355,045,985.77
Open contractor activityOther things to check
0 other flags on this contract
No published item needs checking under the current rules.