Budget concentration investigation
Where are FY2027 House-stage project-list changes concentrated?
Busisi compared 20,431 rows across four project lists, then grouped the document differences by recorded program, region, office, and dataset labels.
Direct answer
The differences are unevenly distributed, but a cluster is only a place to check.
9,283 rows are not classified as unchanged in the source comparison. Of those, 6,954 are classified as House-list only. A repeated label can help prioritize source-page review, but it cannot explain who caused a change or why.
Largest recorded clusters
Region IV-A has the largest House-only row count in the scoped regional labels at 782.
Convergence and Special Support Program has the largest House-only row count among recorded program labels at 5,053.
By region label
Regional labels with the most House-only rows.
Quarantined rows remain visible in the package but do not become findings.
| Recorded region | House-only | Available for review | Share of House-only rows | Recorded amount |
|---|---|---|---|---|
| Region IV-A | 782 | 681 | 11.25% | ₱24.38B |
| Region I | 777 | 762 | 11.17% | ₱13.86B |
| Region III | 692 | 641 | 9.95% | ₱23.21B |
| Region II | 548 | 534 | 7.88% | ₱11.47B |
| Region X | 468 | 443 | 6.73% | ₱15B |
| Region XII | 421 | 396 | 6.05% | ₱4.66B |
| Region VI | 403 | 364 | 5.80% | ₱8.42B |
| Region V | 335 | 313 | 4.82% | ₱14.78B |
| Region VII | 307 | 297 | 4.41% | ₱8.01B |
| NCR | 268 | 246 | 3.85% | ₱13.91B |
| Region XI | 252 | 248 | 3.62% | ₱8.29B |
| Region VIII | 232 | 230 | 3.34% | ₱7.22B |
By program label
Program labels identify a narrower document-review queue.
| Recorded program | House-only | Available for review | Share of House-only rows | Recorded amount |
|---|---|---|---|---|
| Convergence and Special Support Program | 5,053 | 4,713 | 72.66% | ₱100.95B |
| Flood Management Program | 478 | 450 | 6.87% | ₱27.99B |
| REPAIR/REHABILITATION AND CONSTRUCTION OF FARM-TO-MARKET ROADS IN DESIGNATED KEY PRODUCTION AREAS | 355 | 355 | 5.10% | ₱5.97B |
| Asset Preservation Program | 344 | 339 | 4.95% | ₱19.83B |
| Network Development Program | 221 | 207 | 3.18% | ₱17.94B |
| 1. Primary Care Facilities | 95 | 95 | 1.37% | ₱236.25M |
| 2. LGU Hospitals | 79 | 79 | 1.14% | ₱2B |
| Establishment of Pump Irrigation Sub-Program | 78 | 78 | 1.12% | ₱2.18B |
| Bridge Program | 71 | 70 | 1.02% | ₱4.1B |
| National Irrigation System Sub-Program | 71 | 71 | 1.02% | ₱2.92B |
| Communal Irrigation System Sub-Program | 62 | 62 | 0.89% | ₱1.95B |
| Local Program | 26 | 25 | 0.37% | ₱1.34B |
| 7. Other Health Care Facilities | 6 | 6 | 0.09% | ₱91M |
| Special Irrigation Sub-Program | 6 | 6 | 0.09% | ₱23.9M |
| Other Irrigation System Sub-Program | 3 | 3 | 0.04% | ₱240M |
| 3. DOH Hospitals | 2 | 2 | 0.03% | ₱60M |
| Extension/Expansion of Existing Irrigation System Sub-Program | 2 | 2 | 0.03% | ₱70M |
| 5. Drug Abuse Treatment and Rehabilitation Centers | 1 | 1 | 0.01% | ₱15M |
| 8. State Universities | 1 | 1 | 0.01% | ₱2M |
| 4. BUCAS | 0 | 0 | 0.00% | ₱0 |
| 5. Completion of Drug Abuse Treatment and Rehabilitation Centers | 0 | 0 | 0.00% | ₱0 |
| 6. Bureau of Quarantine | 0 | 0 | 0.00% | ₱0 |
| National Building Program | 0 | 0 | 0.00% | ₱0 |
By office label
Office labels provide administrative context, not responsibility.
“Not stated” is preserved rather than guessed. An office label does not establish sponsorship, authorship, control, or benefit.
| Recorded office | House-only | Available for review | Share of House-only rows | Recorded amount |
|---|---|---|---|---|
| Central Office | 1,001 | 939 | 14.39% | ₱104.28B |
| Not stated | 761 | 761 | 10.94% | ₱15.75B |
| Ilocos Norte 1st District Engineering Office | 405 | 405 | 5.82% | ₱4.37B |
| South Cotabato 2nd District Engineering Office | 266 | 257 | 3.83% | ₱1.72B |
| Isabela 4th District Engineering Office | 151 | 147 | 2.17% | ₱1.71B |
| Nueva Ecija 1st District Engineering Office | 124 | 107 | 1.78% | ₱1.51B |
| Cavite 1st District Engineering Office | 112 | 112 | 1.61% | ₱846M |
| Bohol 1st District Engineering Office | 107 | 107 | 1.54% | ₱1.49B |
| Pangasinan 3rd District Engineering Office | 102 | 95 | 1.47% | ₱602.5M |
| Batangas 2nd District Engineering Office | 97 | 77 | 1.39% | ₱1.52B |
| Davao de Oro 1st District Engineering Office | 96 | 96 | 1.38% | ₱1.74B |
| Misamis Occidental 2nd District Engineering Office | 91 | 91 | 1.31% | ₱1.81B |
Largest matched amount changes
Amount movement ranks records for inspection, not suspicion.
Each example matched across both documents. The values are proposed authority, not releases, payments, final cost, or outcome.
Evidence boundary
A ranking cannot answer motive or final outcome.
Busisi still needs later Senate, bicameral, enacted GAA, release, procurement, payment, and implementation evidence to establish whether a House-stage difference survived or produced public value.
Reproduce the result
Every table comes from the same authenticated release.
Dimensions overlap and must not be added together. Counts, examples, limitations, and source identities are available in the immutable package.