Budget-stage investigation

What changed between the FY2027 NEP and House project lists?

Busisi checked 20,431 rows across four project-level lists acquired for this release. The result shows where the documents differ. It does not assign authorship, motive, or wrongdoing.

Direct answer

The compared House lists are larger in total, but the records changed in several ways.

Across the four scoped lists, the recorded House total is PHP 13,729,951,000.00 higher than the NEP total. This is proposed budget authority in four lists, not proof of releases, payments, completed work, or value delivered.

Rows compared20,431All four lists
House-list only6,954Document comparison label
Amount changed508Matched rows
Quarantined426Not promoted as findings

How to read this

“House-list only” is not proof of an insertion.

A row may look new because wording, grouping, scope, or matching changed. The 6,954 source-classified rows are leads for document review. Even the 6,565 rows that passed automated quarantine still need evidence review before any stronger conclusion.

Change ledger

Every row belongs to a stated comparison class.

Comparison classRowsQuarantinedNet document movement
Matched row decreased2650-₱90.52B
House list only6,954389₱187.9B
Matched row increased2430₱6.99B
NEP list only1,7840-₱90.79B
Scope needs review3737₱149.43M
Matched row unchanged11,1480₱0

Covered programs

This is a four-list investigation, not the whole national budget.

Project listRowsHouse-list onlyQuarantinedNet movement
DPWH national infrastructure17,6136,193426₱14.15B
Farm-to-market roads1,0593550₱3.63B
Health facilities7461840-₱4.45B
Irrigation1,0132220₱401.12M

Largest changes to inspect

Open the row before drawing a conclusion.

These examples rank absolute document movement. Size alone is not a red flag or evidence of wrongdoing.

Project recordClassNEP amountHouse amount
Laguna Lakeshore Road Network (LLRN) Project - Phase I, KEDCF Loan No. PHL-27, ADB Loan No. 4523-PHI and AIIB Loan No. L0725ADPWH · NCRMatched row decreased₱35,209,919,000.00₱8,209,919,000.00
Bataan-Cavite Interlink Bridge (BCIB) Project, ADB Loan No. 4432-PHI and AIIB Loan No. L0724ADPWH · NCRMatched row decreased₱22,494,406,000.00₱8,494,406,000.00
Cebu-Mactan Bridge (4th Bridge) and Coastal Road Construction Project, JICA Loan No. PH-P274DPWH · NCRMatched row decreased₱8,570,911,000.00₱2,570,911,000.00
Pasig - Marikina River Channel Improvement Project (PMRCIP), Phase IV, JICA Loan Nos. PH-P271 and PH-P283DPWH · NCRMatched row decreased₱8,539,933,000.00₱3,039,933,000.00
Mindanao Transport Connectivity Improvement Project, IBRD Loan No. 9775-PHDPWH · NCRMatched row decreased₱5,211,754,000.00₱1,711,754,000.00
Davao City Bypass Construction Project (III) (South and Center Sections), Package I, JICA Loan No. PH-P282DPWH · NCRMatched row decreased₱7,420,440,000.00₱3,920,440,000.00

Evidence boundary

426 rows are held back.

Busisi does not turn ambiguous matches or scope-review rows into public findings. The comparison also stops before the Senate, bicameral conference, enacted GAA, release, procurement, payment, and implementation stages.

Reproduce the result

The article, API, and editorial package share one immutable release.

Busisi authenticated the archived overview and source documents, validated every page, and reconciled row counts and money totals before publication.

Source artifact
f47cc042ae08efb6883854b23b230dda25cba073765edfe7aeb84ce509b32177
Package
7cd2b9fc154cdae4228232fae5fd2446bb2b88c5bd82f56823d9e1afd77cca1a