Archived contractor activity

Recorded PCAB ID 8020

SOCOR CONSTRUCTION CORPORATION

Project associations in the acquired DPWH snapshot, FY 2024 to FY 2025.

Project associations
41
Associations, not necessarily unique completed works
Associated project budget
₱2,181,944,900.40
Not revenue, payment, or contract value received
Joint-project associations
10

Recorded status mix

Projects by source status

Completed
25
Ongoing
16
Terminated
0

PCAB verification snapshot

current regular

Listed name
SOCOR CONSTRUCTION CORPORATION
Category
AAA
Valid to
2029-09-24
Verify in the current PCAB table

Recorded project ledger

Projects associated with this recorded identity

31 sole-project associations and 10 joint-project associations. 12 project associations currently have at least one deterministic review signal.

Sole-project associated budget
₱909,907,700.19
Full project values for records naming only this party
Joint-project associated budget
₱1,272,037,200.21
Full project values, not an allocation to this party

Loading structured project associations...

Contractor accountability

No strongly matched accountability event is published

A missing event is not clearance. Name-only and unmatched records remain quarantined and are not shown.

Review leads

Signals associated with this contractor identity

  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGE PAVED ROADS SECONDARY ROADS, LEMON-LEYTE-BILIRAN RD, K0979+796-K0979+850, K0983+657-K0983+706, K0987+532-K0988+628, K0988+660-K0988+698, K0988+798-K0988+881, K0989+179-K0989+199, K0989

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGE PAVED ROADS SECONDARY ROADS, LEMON-LEYTE-BILIRAN RD, K0979+796-K0979+850, K0983+657-K0983+706, K0987+532-K0988+628, K0988+660-K0988+698, K0988+798-K0988+881, K0989+179-K0989+199, K0989

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K1045+603 - K1045+1048, K1045+1064 - K1046+720, SOUTHERN LEYTE 2ND LD

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K1029+003 - K1030+000, SOUTHERN LEYTE 2ND LD

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K1046+736 - K1047+038, K1047+106 - K1047+734, SOUTHERN LEYTE 2ND LD

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS LILOAN - S RICARDO RD - K1072+532 - K1073+129, SAN FRANCISCO, SOUTHERN LEYTE

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MT PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RD (CALANAN-PINUKPUK SECT), K0512+000- K0513+398, K0514+000-K0515+000

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MALALAO NAT'L RD (AGBANNAWAG-MALALAO-BULO SECT), K0514 + 000 - K0516 + 000, K0512+716 - K0513+000, K0516+415 - K0520+0

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - BULANAO-PARACELIS RD, K0508 + 645 - K0513 + 1105

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DALAGUETE RIVER (DOWNSTREAM) AT BARANGAY POBLA

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: OO1 :ASSET PRESERVATION PROGRAM-REHAB./ RECONST./ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - CEBU NORTH HAGNAYA WHARF RD (S00286CB) K0011 + 657 - K0012 + 948 MODIFIED TO: CNHWR - K0012+139 - K0012+862), CONSOLACION, CEBU

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO CAMBARKO, BARANGAY LANAO, DALAGUETE, CE

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged
  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM -PREVENTIVE MAINTENANCE - TERTIARY ROADS - AS FORTUNA ST- CHAINAGE 0 - CHAINAGE 129, CHAINAGE 0 - CHAINAGE 129, CEBU CITY

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged
  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM -PREVENTIVE MAINTENANCE - TERTIARY ROADS - AS FORTUNA ST- CHAINAGE 0 - CHAINAGE 129, CHAINAGE 0 - CHAINAGE 129, CEBU CITY

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged

Concentration context