Something to check, not a finding

The recorded place may not match · Contract 25IE0013

Several projects use the same coordinates

ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGE PAVED ROADS SECONDARY ROADS, LEMON-LEYTE-BILIRAN RD, K0979+796-K0979+850, K0983+657-K0983+706, K0987+532-K0988+628, K0988+660-K0988+698, K0988+798-K0988+881, K0989+179-K0989+199, K0989

Recorded project budget
₱94,519,513.92
Status / progress
On-Going / 100.0%
Location
Leyte 3rd DEO, Region VIII

Why Busisi flagged this

What we noticed

Coordinate 11.4216382, 124.4828866 is shared by: 25IE0013, 25IE0016, 25IE0025, 25IE0036, 25IE0048, 25IE0061, 25IE0067, 25IE0074, 25IE0075, 25IE0078.

Why check it: The exact same point appears on more than one project record.

What to check next: Compare the project titles, places, scopes, images, and site plans.

Technical details

Shared coordinates can represent adjacent works or a common site and are not proof of duplicate funding.

Rule code
reused_coordinate
Snapshot fingerprint
5b411cf3f112fabd…
Open the project record

Office-linked congressional context

Leyte 3rd DEO

  • Leyte, 3rd DistrictVeloso-Tuazon, Anna Victoria

District context is inferred only from the listed DPWH office. It does not show who requested, sponsored, controlled, or is responsible for a project or amount.

Recorded contractor identities

Every party stated in the project record

Other things to check

1 other flag on this contract

  • The record disagrees with itselfThe project says ongoing, but progress says 100%

    What we noticed: Status is On-Going; reported progress is 100.0%.

    What this does not prove: This mismatch does not prove that the project is unfinished or that anyone did something wrong.

    See why this was flagged