Something to check, not a finding

We do not have enough information yet · Contract 24C00091

The record says completed, but this source has no satellite image

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN MIGUEL RIVER, BARANGAY SIBUL, SAN MIGUEL, BULACAN, PACKAGE IX

Recorded project budget
₱96,498,948.96
Status / progress
Completed / 100.0%
Location
Region III, Region III

Why Busisi flagged this

What we noticed

The record is completed but the snapshot reports no satellite image.

Why check it: A listed image field is missing from the acquired record for a completed project.

What to check next: Check project images, inspection records, and completion documents.

Technical details

Absence from this field is not proof that implementation evidence does not exist.

Rule code
completed_without_satellite_image
Snapshot fingerprint
5b411cf3f112fabd…
Open the project record

Congressional context

No exact office attribution available

The listed office did not match a published office-to-district mapping.

Recorded contractor identities

Every party stated in the project record

PCAB 50470

IRONCUE CONSTRUCTION AND SUPPLY INC.

3 archived project associations · ₱367,904,194.54

Open contractor activity

Other things to check

1 other flag on this contract

  • The recorded place may not matchSeveral projects use the same coordinates

    What we noticed: Coordinate 15.1688, 121.0524 is shared by: 24C00091, 24C00514.

    What this does not prove: Projects can share a site, entrance, office, or map point. Reuse does not prove duplication.

    See why this was flagged