The recorded place may not match · Contract 24C00091
Several projects use the same coordinates
FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN MIGUEL RIVER, BARANGAY SIBUL, SAN MIGUEL, BULACAN, PACKAGE IX
- Recorded project budget
- ₱96,498,948.96
- Status / progress
- Completed / 100.0%
- Location
- Region III, Region III
Why Busisi flagged this
What we noticed
Coordinate 15.1688, 121.0524 is shared by: 24C00091, 24C00514.
Why check it: The exact same point appears on more than one project record.
What to check next: Compare the project titles, places, scopes, images, and site plans.
Technical details
Shared coordinates can represent adjacent works or a common site and are not proof of duplicate funding.
- Rule code
- reused_coordinate
- Snapshot fingerprint
5b411cf3f112fabd…
Congressional context
No exact office attribution available
The listed office did not match a published office-to-district mapping.
Recorded contractor identities
Every party stated in the project record
ADSL CONSTRUCTION & TRADING
92 archived project associations · ₱5,974,371,380.52
Open contractor activityIRONCUE CONSTRUCTION AND SUPPLY INC.
3 archived project associations · ₱367,904,194.54
Open contractor activityOther things to check
1 other flag on this contract
- We do not have enough information yetThe record says completed, but this source has no satellite image
What we noticed: The record is completed but the snapshot reports no satellite image.
What this does not prove: A missing image does not prove that work was not completed.
See why this was flagged